Base preparation

   Concrete or cement basis should be not less than 28 days «old», the temperature – not less than +5° and the strength not less than 20 MP. All construction joints, gaps, cracks and holes, which can create leakage of the mixture, must be filled in. All defects must be cured. A dempfer tape must be laid along the perimeter (and columns) of the floor. 

   The surface must be cleaned from any dust, mud, oil or bitumen spots, paint, etc. The surface must be treated with a floor primer IVSIL TIE-ROD. In case of capillary raise of humidity, the surface should be covered with a layer of hydro-insulation mix IVSIL VODOSTOP.

Mixing of mortar

   Pour the content of a mix pack into a mixing bucket with clean water in the proportion of 25 kg (whole pack) of dry mix per 5,5 L of water and thoroughly stir it with the help of a mixing drill until homogeneous mixture is received. Leave it for 5 minutes, then stir again. Ready mixture should be used within 0,5 hour since it was prepared. Adding to much water to the mix may result in loosing strength characteristics of the mixture and appearance of cracks when the floor has dried.

Application

Pour ready mixture on prepared surface, float and spread it evenly with the help of walking trowel or float. Roll a needle roller over the surface to get rid of air bubbles in the mixture. If the area is more than 20 square metres, it is necessary to treat deformation joints. Floor levelling should be done in one go without technological breaks. 

   Do not allow draughts, direct sunshine or sharp changes of temperature or humidity whilst the floor is getting dry. Air and basis temperature must be from +5C to +30C. Further application of floor decoration materials should follow instructions of manufacturers. Do not forget to control basis humidity level (not before 14 days!).

 
Consultation on the pplication materials

TIE-ROD-II

  

   Final thin self-levelling floor mix TIE-ROD-II is made of high quality cement, fractioned sand, mineral fillers and polymer additives. It is designed for final levelling of the surface and creating even smooth horizontal layer over sand-cement and concrete screeds prior to further cover with decorative materials (linoleum, laminate, carpetlin, parquet, ceramic tiles, etc.)

   This finishing floor mix is easy to float and spread over the surface, has a high level of adhesion with basis. Strength of this floor is enough to sustain normal walking load of different types of premises. IVSIL TIE-ROD-II is frost resistant and can be used for exterior jobs. It is water resistant and humidity resistant. This self-levelling mix can be used in all types of premises with normal and high level of humidity.

   Having dried, this mixture forms a thin, solid and perfectly even surface. It is ideal for use in «heated floor» (underfloor heating) systems, it can be poured over it in order to minimise warmth loss. The basic price of thin self-levelling floor IVSIL TIE-ROF-II is 355 roubles/25 kg. To see prices of other IVSIL floor levelling mixes, please visit the section «Price List».

   See also: floor levelling mix for preliminary levelling IVSIL TIE-ROD-I, rapidly hardening finishing floor mix IVSIL EXPRESS-FINISH, floor primer IVSIL TIE-ROD or go back to the section all IVSIL Flooring mixes.

   Dry flooring mixes IVSIL: thin self-levelling cement finishing floor IVSIL TIE-ROD-II, floor levelling mix for heated floors.

 
 

Technical characteristics

Mixing proportion: 1l of water
On 1 kg of a mix0,21 0,23 l
On 25 kg of a mix5,25 5,75 l
The consumption at a thickness of a layer of 1 mm, on 1 sq. m1,2 1,5 kg
Thickness of a layer of a solution, mm2 10 mm
Viability of a solution30 min
Hardening time1 2 day
Temperature of works and the baseFrom +5 to +30
Durability on compression15 MPa
Frost resistance50 cycles
Packaging25 kg
Colorgrey
 
Packaging and storage
The dry mix is delivered in kraft-bags on 25 kg. A storage warranty period is 6 months from the date of the manufacturing.
The consumption
The average expense 4 kg of a dry mix on 1 m. of a sq. surface at a thickness of a layer of 3 mm. The exact expense depends is degree of flatness (relief) of the basis.
 